Project running late: how to replan the timeline without losing control
When a critical task slips, pushing every date back rarely solves anything. See how to measure the impact, choose how to win back time and rebuild the plan with your team.
The supplier’s email at the end of week 3
A twelve-person accounting firm had eight weeks to move, because the lease on the old office ended then. The plan was simple: layout and furniture order in week 1, painting and electrical work in weeks 2 and 3, workstation delivery in week 4, assembly and then the network, a week of buffer and the move in week 7.
At the end of week 3, the supplier’s email arrived: the workstations would be two weeks late. The first reaction was to push everything forward on the timeline and hope. But pushing dates isn’t replanning. It only records the delay, and here it would push the move into the last week of the lease, with no room for anything else to go wrong.
First, do the math: how far the delay pushes the end
Not every delay moves the end date. A task with slack can slip a few days with no effect; a task on the critical path pushes everything that depends on it, day for day. The workstation delivery was on the critical path: no desks, no assembly, and no assembly, no move.
You work it out along the dependency chain. Start from the late task’s new date, move through the tasks that depend on it and see where the last one lands. At the firm, a two-week delay against one week of buffer left the move one week later, right up against the end of the lease. If the buffer had covered the delay, the plan would have stood, with the buffer use recorded. Since it didn’t, they had to recover time or accept another date.
One-off or recurring? The question before touching dates
Before choosing a fix, the partners called the supplier. The cause was a factory backlog, not a problem with their order. That mattered for two reasons. A one-off delay calls for a local adjustment. A delay from a cause that’s still active can happen again, and the new plan has to account for it.
So the firm asked the supplier for the new date in writing and agreed on a confirmation in week 5. If the pattern had been different, say the team itself underestimating every task in a phase, the conclusion would change: the later phases, estimated the same way, were probably optimistic too.
The levers, and why some were ruled out
There are only a few ways to recover time, and each has a cost. The partners went through all of them before deciding:
- Negotiate the date: ruled out. The lease ended at the end of week 8, and another month would be expensive.
- Add people: ruled out. The supplier’s crew does the assembly, and more office staff wouldn’t help. Fred Brooks, in The Mythical Man-Month, observed that adding people to a late software project tends to make it later. The idea holds outside software: extra hands only help on tasks that can be split, done by people who already know how.
- Reorder: chosen. The network depended only on the building work, not on the desks, because each workstation’s position was already in the layout. It could be installed during the wait.
- Reduce or split the scope: chosen. The meeting room furniture doesn’t stop anyone from working and could wait until after the move.
The new plan
With the network moved up to weeks 4 and 5, waiting for the workstations stopped being lost time. With the meeting room left out of the first assembly, assembly got shorter. Delivery moved to week 6, assembly filled that week, three days of buffer remained and the move stayed in week 7. The firm would open at the new address at the start of week 8, with the meeting room as a second phase.
The buffer is smaller than the original, but it’s an explicit buffer, named on the timeline, not the hope that nothing else slips. The old plan was kept for the wrap-up, when the partners wanted to review how they negotiate deadlines with suppliers.
When the date isn’t fixed
The choice of levers came down to one question: what can’t change? When the date is fixed, like a lease, a scheduled event or the end of a contract, you’re left with scope, sequence and staffing. When the scope is fixed, because half a delivery is useless, the way out is usually to negotiate the deadline. Keeping both fixed and changing nothing else is the recipe for a timeline nobody believes.
Running tasks in parallel or reordering them has risks too. It’s only safe when one task doesn’t change the outcome of the other. Installing the network before the desks worked because the layout was settled; if the workstation positions had still been under discussion, moving it up could have meant rework. And overtime, which looks free, wears the team down and often causes the next delay.
Rebuild the plan from today
The new timeline doesn’t rewrite the past. Mark what’s done, update progress on what’s underway and re-estimate what’s left with the people who will do it, using what the delay taught you. Then apply the lever you chose, adjust dependencies, check whether the critical path changed and recreate a buffer for the remaining stretch. Keep a copy of the previous version before you change anything.
In the Qriou.org timeline, each task has dates, an owner, a status, progress and a dependency, which you can change when the order changes, as happened with the network. Milestones show up as points on the plan. Export the plan to CSV before editing it, and the old version stays available to compare planned and actual at the end.
Tell everyone at once
That same day, the partners sent one message to the whole team, the contractor and the IT technician: what changed, why, and what each of them needed to do differently. The technician, who expected to start in week 5, learned a week ahead that he’d start sooner. Anyone who depends on a changed date should hear about it before finding out on their own.
The message was also clear about the uncertainty that remained: the supplier’s new date would be confirmed in week 5, and if it slipped again, the meeting room wouldn’t be the only cut. Saying what the uncertainty is and when it will be settled keeps more trust than announcing an optimistic date and having to push it back again.